Construction Photographs, weeks 11-15
4 November - end of week 15
Photovoltaic Cells fitted to generate electricity for the building. Even on a relatively overcast autumnal day the array was generating 11 kW of power.
23 October - end of week 13 of 27
Internal wall partitions 70% complete. External cladding commenced. Electrical 1st fit commenced. Roof 95% complete.
15 October - end of week 12
Internal spaces starting to evolve as external and internal walls are constructed well within the allocated time.
Familiar view from the Willows Education Peninsula as the pond planting takes shape.
Mayor and Council leader of Broxtowe prepare for the topping out ceremony on 15/10/04.
7 October
Roof nearly complete. Photovoltaic cells to be fitted in next 3 weeks. Work now starts on the external walls.